Back to News

New Premises - April Update Posted on 18 Apr 2018

The foundations and the land drainage are complete with the site levels being made up steadily to the proposed finished levels. The Lower Ground Floor blockwork is approaching completion and the waterproofing has commenced.

The primary steels in the Lower Ground Floor are being erected at the end of the month so that the Ground Floor concrete planks and the stairs can be lifted into place straight after the May Bank holiday. The SIPs panel system which is the framework of the remainder of the building will start to be erected at the end of May. Despit the weather we have experence the project remains on programme for internal fitting out before the end of the year.